Ecosan Greywater Demonstration Project. Case study from Kuching, Malaysia

The city of Kuching is currently lacking a wastewater treatment plant, and the local subsurface conditions make a conventional centralised wastewater system expensive to implement. Most buildings are equipped with two separate wastewater outlets, one outlet for blackwater and one for greywater. The proposed system treats greywater from nine households, and consists of a baffled septic tank, followed by a dosing chamber from where the greywater flows into four vertical down-flow, single-pass aerobic biofilters before reaching a subsurface horizontal-flow planted filter. Finally, the treated greywater is discharged into a stormwater drain.

MOREL A. DIENER S. (2006): Ecosan Greywater Demonstration Project. Case study from Kuching, Malaysia. In: MOREL, A. ; DIENER, S. ; (2006): Greywater Management in Low and Middle-Income Countries, Review of Different Treatment Systems for Households or Neighbourhoods. Duebendorf: 76-79.